Task |
26th October
publication |
Procurement process |
|
Advert published on Contracts Finder / FTS /In-Tend & ITT issued |
Tuesday 26th October 2021 |
Site visits (if possible/if necessary) |
W/C 8th November |
Deadline for receipt of ITT clarification questions |
2nd December |
Deadline for receipt of ITT submissions |
Thursday 16th December 2021 |
ITT compliance checks |
16th December - 20th December |
Selection Questionnaire evaluation (if questions require subject matter experts) |
20th December - 24th December/early Jan |
ITT Evaluation (individual evaluations) |
21st December - 26th January 2022 |
Moderation meetings |
1st February - 28th February 2022 |
Draft CARR & Debrief letters |
W/C 28th February & W/C 7th March 2022 |
Approval to proceed (procurement and NHSEI) |
W/C 14th March
(Proc) |
Approval to proceed (OPCCs & Police) |
W/C 28th March & W/C 4th April 2022 |
Inform bidders of outcome – Preferred Bidder stage (if required) |
11th - 26th April 2022 |
Standstill period |
27th April - 9th May 2022 |
Contract award |
10th May 2022 |
Mobilisation |
Mid May - September 2022 |
Service commencement |
1st October 2022 |